ETL 189

Schleswig-Holstein – Hydrogen Bridge for Northern Germany

Hydrogen is one of the key components of the energy transition and will play an essential role in enabling German industry to achieve CO2 neutrality. This will only be possible if the infrastructure required to transport hydrogen is in place. Schleswig-Holstein, in particular, occupies a central position due to its proximity to the large volumes of hydrogen expected to be available in Denmark. To support this, Gasunie is planning to construct and subsequently operate the 22-kilometre Energy Transport Pipeline (ETL) 189 from Oberglinde to Klein Offenseth.

Timeline (as of Nov. 2026)
October 2024 Feasibility study
September 2025 Start of ground investigations and further preliminary surveys
November 2026 Information events marking the start of the Right of Way acquisition process
Q4 2026 Submission of the planning approval application
Q1 2027 “Gasunie vor Ort” – public information events
Q4 2027 Potential start of early construction works, subject to approval
Q1 2028 Receipt of the planning approval decision; anticipated start of construction
End of 2028 / beginning of 2029 Technical completion
Q1 2029 Operational readiness

To supply Germany with climate-neutral hydrogen in the future, a high-performance transport infrastructure is required. The foundation for this is the national hydrogen core network, which was approved by the Federal Network Agency in October 2024. Through its Hyperlink project, Gasunie Deutschland, as a transmission system operator within the meaning of the German Energy Industry Act (EnWG), is actively involved in developing this network.

The construction of the new Energy Transport Pipeline (ETL) 189 between Oberglinde and Klein Offenseth is an important building block of Germany’s hydrogen network. Due to its proximity to Denmark, one of the most important future producers of green hydrogen, Schleswig-Holstein has a key role to play in the energy transition. Within Hyperlink, ETL 189 forms part of the Hyperlink 3 sub-project. ETL 189 enables these hydrogen volumes to be transported to key industrial regions in Germany and north-western Europe.

As part of the hydrogen core network, ETL 189 will also enable future projects in Schleswig-Holstein to connect to the German and European hydrogen infrastructure. This applies both to potential production and import sites, for example on Germany’s North Sea coast, and to potential consumers in the vicinity of the newly constructed pipeline.



ETL 189 – Facts and Figures
District affected Kreis Pinneberg
Total length 24 km
Nominal pipe diameter 900 mm
Maximum operating pressure (MOP) 84 bar
Medium Hydrogen
Width of protective strip 10 m
Width of standard working strip 38 m
Width of restricted standard working strip 18 m